Update: power was reported restored by 12:03 p.m.
Hydro said the outage was related to a contractor (non BCH) doing work that 鈥渃reated a fault in the circuit.鈥
BC Hydro had to investigate to make sure everything was safe before reenergizing,鈥 a Hydro spokesperson said.
Power was fully restored at 12:03 pm.
Close to 3,000 BC Hydro customers in 91原创 lost power at 11:30 a.m. Sunday morning.
Affected area is west of 272nd Street, north of 30th Avenue, east of 240th Street and south of 56th Avenue, a BC Hydro update said.
We're aware of the outage near impacting 2,985 customers. Crews are on their way and updates are available on:
鈥 BC Hydro (@bchydro)
BC Hydro said crews have been dispatched.
READ ALSO: Heat wave sets new record for peak hourly demand: BC Hydro
READ ALSO: 91原创 was one of the hardest hit during Lower Mainland windstorm, BC Hydro says
Have a story tip? Email: dan.ferguson@langleyadvancetimes.com
Like us on and follow us on .